Work Profile Report [140W6]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1603/VI(1)/2021-03(85)/2021
TS Amount (lakhs) : 2158.99 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2158.99
Resanction Cost :
2158.99
Tentative Cost :
2158.99
Exp. Upto Last Fy :
1,933.59
For CFY 2025-2026
Remaining :
225.40
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1,933.59
Construction Started
Sanction on : 3 years 6 months ago
17 Nov 2021
Physical Progress:
At start of FY 2025-2026 :
96 %
Up to Date :
96 %
Tentative Completion date on : 10 months 1 week ago
31 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
FOOTPATH COBBLE & MEPF WORK IN PROGRESS. -- as on 02-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: