Work Profile Report [15W213]

जनपद पिथौरागढ में भण्डारीगाॅव रजवार बोक्टा धुराली मोटर मार्ग का नव निर्माण (मु0घो0सं0 138/2010)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

Administrative Approval Detail : शां0स0 5519/(1)/।।।(2)/10-06 (मु0म0घा0) /2010 दिनांक 15-10-2010

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

126.00

Resanction Cost :

126.00

Tentative Cost :

126.00

Exp. Upto Last Fy :

47.51

For CFY 2024-2025

Remaining :

78.49

Demand :

75.65

Allotment :

0.00

Exp in CFY :

5.48

Total Up to Date Exp :

52.99

Work completed

Sanction on : 13 years 10 months ago

15 Oct 2010

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 1 year 7 months ago

31 Dec 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
10
10
20.000
-10
0.000
0.000

Remark

view all

कार्य पूर्ण। प्रभागीय वनाधिकारी के पत्रांक संख्या 817/12-1 दिनांक 22.08.2022 से एन0पी0वी0 धनराशि पुनः नदी दरों पर जमा कराने हेतु लिखा गया है , मार्च 2024 में बडी हुई दरों पर NPV की धनराशी वन विभाग के पक्ष में जमा की जा चुकी है। वर्तमान में नाप भूमि का मुआवजा वितरित किया जा रहा है। मार्ग पर कुछ काशनतकारों द्वारा मुआवजा कब्जाधारकों को वितरित किए हेतु मा० तहसीलदार न्ययालय में अग्रिम कार्यवाही तक रोक लगाने हेतु वाद दाखिल किया गया है। जिससे कारतकारों को ₹70.00 लाख का भुगतान नहीं किया जा सका। -- as on 11-Apr-2024

Rating : 100

Forest Case Pending At : 14: AIP Conservator

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: