Work Profile Report : 15W367

जनपद पिथौरागढ के विधानसभा क्षेर्त पिथौरागढ मे दिगरा से तडीगांव मोटर मार्ग का निर्माण।मु0मं0 धोषणा से 98/2012।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : 2195-1/।।।-2/13-47 प्रा0आ0/2012 दि022-03-2013

TS Amount (lakhs) : 22.27 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

88.20

Resanction Cost :

88.20

Tentative Cost :

88.20

Exp. Upto Last Fy :

1.87

For CFY 2025-2026

Remaining :

86.33

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

1.87

Work deferred

Sanction on : 12 years 10 months ago

22 Mar 2013

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

0 %

Tentative Completion date on : 5 years 10 months ago

31 Mar 2020

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
7
7
7
-

Remark

view all

दिगरा से तडीगांव तक वर्तमान में अन्य एजेंसी द्वारा निर्मित मार्ग से संयोजिता प्रदान होने के कारण ,उक्त स्वीकृती के निरस्तीकरण हेतु इस कार्यालय के पत्रांक 141/01 याता दिनाँक 15/01/26 से निरस्तीकरण प्रस्ताव गठित कर अग्रिम कारवाई हेतु प्रेषित | निरस्तीकरण प्रस्ताव मुख्य अभियन्ता लोक निर्माण विभाग अल्मोडा के पत्रांक 153/03 याता0-अ0/2026 दिनांक 21.01.2026 द्वारा प्रमुख अभियन्ता एंव विभागाध्यक्ष , लोक निर्माण विभाग , देहरादून को प्रेषित है। -- as on 22-Jan-2026

Rating : 2

Forest Case Pending At : 02: Division

Hindrance / Bottleneck : To Cancel

Assets :

Work not linked with IM