Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.8 | 3.8 | 3.8 | 0 |
15W470 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 540/।।।(2)/16-44(एम0एल0ए0)/2015 दिनांक 03/03/2016
TS Amount (lakhs) : 184.5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
184.50
Resanction Cost :
184.50
Tentative Cost :
184.50
Exp. Upto Last Fy : 63.01
For CFY 2024-2025
Remaining : 121.49
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 63.01
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
8 years 4 months ago
03 Mar 2016
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
इस कार्यालय के पत्रांक संख्या 2850/22 याता0 दिनांक 28.11.2018 से अनुपालन आख्या प्रभागीय वनाधिकारी को प्रेषित । इस कार्यालय के पत्रांक 3116ध्22 याता0 दिनांक 03.12.2022 को अनुस्मारक पत्र प्रभागीय वनाधिकारी को प्रेषित । दिनांक 12.02.2024 द्वारा बडी हुई दरों पर ण्न0पी0वी0 की धनराशि आन लाइन चालान के माध्यम से प्रभागीय वन विभाग के पक्ष में जमा की जा चुकी है । -- as on 02-May-2024
Physical Peramenters