Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 8 | 0 |
15W673 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 7034/।।।(2)/18-43 (एम0एल0ए0) /2017 टी0सी0-1 दिनांक 20.12.2018
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 245.60 Lacs
Resanction Cost : 245.60 Lacs
Exp. Upto Last Fy : 1.43 Lacs
For CFY 2024-2025
Remaining : 244.17 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.43 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
5 years 4 months ago
20 Dec 2018
Tentative Completion date:
1 year 4 months ago
31 Dec 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
समरेखन आपत्तियों में खण्ड को प्राप्त । आपत्तियों का निराकरण कर पुनः स्वीकृति हेतु गठित किया जा रहा है। प्रकरण खण्ड स्तर पर लम्बित है। -- as on 11-Apr-2024
Physical Peramenters