Work Profile Report [15W762]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : GO. No. 2368/III(2)/19-44 (MLA)/2017 T.C. Dated 04.07.2019
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
30.56
Resanction Cost :
30.56
Tentative Cost :
30.56
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
30.56
Demand :
20.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 5 years 5 months ago
04 Jul 2019
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण , पी0सी0आर0 गठित की जानी है। -- as on 04-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand