Work Profile Report [15W766]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : File No. PWD2-CW/R/57/2022-III-2-Public Works Department (Computer No. 31646)
TS Amount (lakhs) : 36.32 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
36.32
Resanction Cost :
36.32
Tentative Cost :
26.53
Saving
9.79
Exp. Upto Last Fy :
13.21
For CFY 2024-2025
Remaining :
23.11
Demand :
22.98
Allotment :
0.00
Exp in CFY :
0.35
Total Up to Date Exp :
13.56
Construction Started
Sanction on : 1 year 11 months ago
20 Dec 2022
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
90 %
Tentative Completion date on : 7 months 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 9.79 has been recorded as expected cost of work reduced from 36.32 to 26.53 . -- as on 21-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: