Work Profile Report [15W863]
Tenders
Project Activities
alerts
Administrative Approval Detail : E File No. 53524 Lok Nirman Anubhag-2 dt 26-09-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
58.01
Resanction Cost :
58.01
Tentative Cost :
54.00
Saving
4.01
Exp. Upto Last Fy :
14.27
For CFY 2024-2025
Remaining :
43.74
Demand :
45.00
Allotment :
0.00
Exp in CFY :
14.51
Total Up to Date Exp :
28.78
Construction Started
Sanction on : 10 months 3 weeks ago
26 Sep 2023
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
75 %
Tentative Completion date on : 3 months 4 weeks from now
15 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 4.01 has been recorded as expected cost of work reduced from 58.01 to 54.00 . -- as on 30-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: