Administrative Approval Detail : ltr no. 6203/III(2)/44-04 (CM Gho)/2014 T.C. dt 21-11-2014
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
36.05
Resanction Cost :
36.05
Tentative Cost :
36.05
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
36.05
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Unstarted Work
Sanction on : 11 years 3 weeks ago
21 Nov 2014
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
नव निवर्वचित ग्राम प्रधान से वार्ता हुई है विवाद का समाधान होने पर सर्वेक्षण कार्य किया जायेगा। -- as on 03-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: