Work Profile Report [16W263]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 3519/।।।(2)/14-09(प्रा0आ0)/2014 दिनांक 26.05.2014 द्वारा प्रशासनिक एवं शा0सं0 1472/।।।(2)/15-09(प्रा0आ0)/2014 दिनांक 23.03.2015।
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
40.05
Resanction Cost :
40.05
Tentative Cost :
40.05
Exp. Upto Last Fy :
2.50
For CFY 2025-2026
Remaining :
37.55
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.50
Work completed
Sanction on : 10 years 9 months ago
23 Mar 2015
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
95 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रथम चरण एवं द्वितीय चरण का कार्य पूर्ण। दायित्व शेष। -- as on 05-Dec-2025
Assets :
Work not linked with IM