Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 6.5 | 6.5 | 0 |
16W296 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 5353/।।।(2)/14-25(प्रा0आ0)/2014 दिनांक 20.10.2014
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
64.08
Resanction Cost :
64.08
Tentative Cost :
64.08
Exp. Upto Last Fy : 2.54
For CFY 2024-2025
Remaining : 61.54
Demand : 8.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.54
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
9 years 8 months ago
20 Oct 2014
Tentative Completion date:
6 years 3 months ago
31 Mar 2018
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रथम चरण का कार्य पूर्ण। भमि प्रतिकर भुगतान शेष। कार्य का पुनरीक्षित समरेखन प्रस्ताव अधी0अभि0तृतीय वृत्त लो0नि0वि0,पिथौ0 के पत्राक 1061/872 सी0-03/2020 दि0 18.02.2020 द्वारा अनुमोदित। जिलाधिकारी के पत्रांक 729/सात-38/2015-16 दिनांक 01-03-2016 द्वारा सिविल भूमि में स्वीक्रति प्राप्त। -- as on 26-Apr-2024
Physical Peramenters