Work Profile Report : 16W303

मा0 मुख्यमंत्री घोषणा के अन्तर्गत जनपद पिथौरागढ़ के विकास खण्ड मुनस्यारी में सैमली तक सड़क का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 2520/।।।(2)/16-64(प्रा0आ0)/2016 दिनांक 18.10.2016

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

18.18

Resanction Cost :

18.18

Tentative Cost :

18.18

Exp. Upto Last Fy :

0.36

For CFY 2025-2026

Remaining :

17.82

Demand :

0.20

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.36

Alignment Approved

Sanction on : 9 years 3 months ago

18 Oct 2016

Physical Progress:

At start of FY 2025-2026 :

55 %

Up to Date :

55 %

Tentative Completion date on : 1 year 1 month from now

31 Mar 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
2
2
0.000
2
0.000
0.000

Remark

view all

वर्तमान में वनभूमि प्रस्ताव नोडल स्तर से आपत्ति के कारण डी0एफ0ओ0 स्तर पर लम्बित। -- as on 06-Feb-2026

Rating : 70

Forest Case Pending At : 04: DFO

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: