Work Profile Report [16W338]

जनपद पिथौरागढ़ के विधान सभा क्षेत्र धारचूला के विकास खण्ड मुनस्यारी में बुंई-पातो तक मोटर मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

  • alerts
  • Documents

Administrative Approval Detail : शा0सं0 7209/।।।(2)/15-09(प्रा0आ0/2014 दिनांक 17.10.2015

TS Amount (lakhs) : 492.98 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

323.65

Resanction Cost :

323.65

Tentative Cost :

303.65

Saving

20.00

Exp. Upto Last Fy :

169.71

For CFY 2024-2025

Remaining :

153.94

Demand :

130.00

Allotment :

55.98

Exp in CFY :

55.98

Total Up to Date Exp :

225.69

Construction Started

Sanction on : 8 years 9 months ago

17 Oct 2015

Physical Progress:

At start of FY 2024-2025 :

80 %

Up to Date :

80 %

Tentative Completion date on : 4 weeks 1 day from now

15 Sep 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
5.65
5.65
1.000
4.65
0.000
0.000

Remark

view all

Overall Saving 20 has been recorded as expected cost of work reduced from 323.65 to 303.65 . -- as on 31-Jul-2024

Rating : 82

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: