Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15 | 15 | 15 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 |
16W362 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 428/।।।(2)/16-14(मु0मं0घो0)/2015 दिनांक 23.01.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
92.10
Resanction Cost :
92.10
Tentative Cost :
92.10
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 92.00
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
8 years 5 months ago
23 Jan 2016
Tentative Completion date:
6 years 3 months ago
31 Mar 2018
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सहायक अभियन्ता चुतर्थ डीडीहाट के पत्रांक 02/1सी0 दिनांक 20.01.2024 द्वारा ग्राम प्रधान धुरौली को विवाद सुलझाने हेतु पत्र प्रेषित। -- as on 20-Feb-2024
Physical Peramenters