Work Profile Report [16W371]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शा0सं0 842/।।।(2)/16-60(प्रा0आ0)/2015 दिनांक 16.02.2016
TS Amount (lakhs) : 380.95 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
380.95
Resanction Cost :
398.93
Tentative Cost :
340.29
Saving
58.64
Exp. Upto Last Fy :
322.30
For CFY 2024-2025
Remaining :
76.63
Demand :
10.00
Allotment :
20.00
Exp in CFY :
0.00
Total Up to Date Exp :
322.30
Work completed
Sanction on : 8 years 6 months ago
16 Feb 2016
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 6 months ago
28 Jan 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 58.64 has been recorded as expected cost of work reduced from 398.93 to 340.29 . -- as on 10-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand