Work Profile Report [16W566]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 3214/।।।(2)/21-42 (एम0एल0ए0)/2017 दि0 27.08.2021
TS Amount (lakhs) : 94.28 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
94.28
Resanction Cost :
94.28
Tentative Cost :
80.28
Saving
14.00
Exp. Upto Last Fy :
26.80
For CFY 2024-2025
Remaining :
67.48
Demand :
15.00
Allotment :
10.00
Exp in CFY :
0.00
Total Up to Date Exp :
26.80
Construction Started
Sanction on : 3 years 3 months ago
27 Aug 2021
Physical Progress:
At start of FY 2024-2025 :
75 %
Up to Date :
75 %
Tentative Completion date on : 1 year 11 months ago
31 Dec 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
2.30 कि0मी0 पहाड़ कटान का कार्य पूर्ण, शेष कार्य प्रगति पर। -- as on 05-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: