Work Profile Report [16W567]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 3214/।।। (2)/21-42 (एम0एल0ए0)/2017 दि0 27.08.2021
TS Amount (lakhs) : 90.47 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
90.47
Resanction Cost :
90.47
Tentative Cost :
90.47
Exp. Upto Last Fy :
18.10
For CFY 2025-2026
Remaining :
72.37
Demand :
22.00
Allotment :
7.14
Exp in CFY :
7.14
Total Up to Date Exp :
25.24
Construction Started
Sanction on : 4 years 3 months ago
27 Aug 2021
Physical Progress:
At start of FY 2025-2026 :
60 %
Up to Date :
60 %
Tentative Completion date on : 3 years 2 weeks ago
25 Nov 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
ग्रामीणों द्वारा विवाद किया जा रहा है। अनुबन्ध के अन्तिमीकरण की कार्यवाही गतिमान। -- as on 29-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2025 PWD Uttarakhand