Work Profile Report [16W576]
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : शा0सं0 493/।।।(2)/21-03(प्रा0आ0)/2018 दिनांक 07.01.2022
TS Amount (lakhs) : 137.85 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
137.85
Resanction Cost :
137.85
Tentative Cost :
137.85
Exp. Upto Last Fy :
61.46
For CFY 2024-2025
Remaining :
76.39
Demand :
70.00
Allotment :
50.00
Exp in CFY :
33.80
Total Up to Date Exp :
95.25
Work completed
Sanction on : 2 years 10 months ago
07 Jan 2022
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 7 months 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष्। -- as on 04-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: