Work Profile Report [16W577]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 6009/।।।-2/21-42 (एम0एल0ए0)/2017 टीसी दि0 11.12.2021
TS Amount (lakhs) : 35.06 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
35.06
Resanction Cost :
35.06
Tentative Cost :
35.06
Exp. Upto Last Fy :
0.38
For CFY 2024-2025
Remaining :
34.68
Demand :
0.20
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.38
Alignment Approved
Sanction on : 2 years 11 months ago
11 Dec 2021
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
30 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
हवाई दूरी प्रमाण पत्र दिनांक 01.05.2024 को प्राप्त। वन भूमि प्रस्ताव गठित किये जा रहे हैं। -- as on 05-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: