Work Profile Report [16W657]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन लोक निर्माण अनुभाग-2 के ई0 फाईल संख्या-52192 दिनांक 27 अक्टूबर 2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
228.81
Resanction Cost :
228.81
Tentative Cost :
228.81
Exp. Upto Last Fy :
51.88
For CFY 2024-2025
Remaining :
176.93
Demand :
140.00
Allotment :
70.00
Exp in CFY :
88.74
Total Up to Date Exp :
140.62
Construction Started
Sanction on : 1 year 3 weeks ago
27 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
5 %
Up to Date :
50 %
Tentative Completion date on : 2 months 1 week from now
05 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सोलिंग, इन्टर कोट, टापकोट का कार्य पूर्ण शेष कार्य प्रगति पर। -- as on 26-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: