Work Profile Report [16W659]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन लो0नि0वि0, अनुभाग 2 के ई0 फाईल संख्या-64236 दिनांक 28 नवम्बर 2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
58.08
Resanction Cost :
58.08
Tentative Cost :
58.08
Exp. Upto Last Fy :
15.85
For CFY 2024-2025
Remaining :
42.23
Demand :
38.00
Allotment :
20.00
Exp in CFY :
15.88
Total Up to Date Exp :
31.74
Construction Started
Sanction on : 1 year 3 weeks ago
28 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
1 %
Up to Date :
70 %
Tentative Completion date on : 1 month 1 week ago
15 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 का कार्य प्रगति पर। -- as on 26-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: