Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1 | 0 |
16W659 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन लो0नि0वि0, अनुभाग 2 के ई0 फाईल संख्या-64236 दिनांक 28 नवम्बर 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
58.08
Resanction Cost :
58.08
Tentative Cost :
58.08
Exp. Upto Last Fy : 15.85
For CFY 2024-2025
Remaining : 42.23
Demand : 38.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 15.85
Construction Started
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 40 %
Sanction on :
7 months 2 weeks ago
28 Nov 2023
Tentative Completion date:
3 months 4 weeks from now
15 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 26-Jun-2024
Physical Peramenters