Work Profile Report [16W690]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : उत्तराखण्ड शासन लोक निर्माण अनुभाग-2 के ई0 फाईल संख्या 52192 दिनांक 06 जून 2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
176.97
Resanction Cost :
176.97
Tentative Cost :
176.97
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
176.97
Demand :
25.00
Allotment :
83.10
Exp in CFY :
83.10
Total Up to Date Exp :
83.10
Construction Started
Sanction on : 7 months 6 days ago
06 Jun 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
35 %
Tentative Completion date on : 3 months 4 weeks from now
12 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
2.00 किमी0 लम्बाई में इन्टरकोट का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 02-Jan-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: