Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
16W97 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5150/।।।(2)/10-18 (प्रा0आ0)/2010 दि0 16.8.2010
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 37.80 Lacs
Resanction Cost : 37.80 Lacs
Exp. Upto Last Fy : 19.52 Lacs
For CFY 2024-2025
Remaining : 18.28 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 19.52 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
13 years 8 months ago
16 Aug 2010
Tentative Completion date:
7 years 1 month ago
31 Mar 2017
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
उक्त मोटर मार्ग हेतु राज्य भूमि प्रस्ताव जिलाधिकारी पिथौरागढ़ के पत्रांक 1711/सात-57/2014-15 दिनांक 08.08.2015 द्वारा स्वीकृत प्रदान की गयी है। कार्य पूर्ण करा लिया गया है। -- as on 03-Jan-2024
Physical Peramenters