Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 30 | 30 | 30 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 |
17W123 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5519(1)/।।।(2)/10-06(मु0मं0घो0)/2010 दि0 15-10-2010
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 388.50 Lacs
Resanction Cost : 388.50 Lacs
Exp. Upto Last Fy : 17.04 Lacs
For CFY 2024-2025
Remaining : 371.46 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 17.04 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
13 years 6 months ago
15 Oct 2010
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 03: DM
Bottelneck: CA Land
प्रभागीय वनाधिकारी द्वारा क्षतिपूरक वृक्षारोपण हेतु चयनित स्थल अत्यन्त तीव्र ढाल होने के कारण अनुपयुक्त बताते हुए अन्य स्थल चयनित करने हेतु आपत्ति में प्राप्त। उपजिलाधिकारी धारचूला को तदानुसार उपयुक्त भूमि उपलब्ध कराये जाने हतु दिनांक 06.01.2024 को पत्र प्रेषित। -- as on 19-Feb-2024
Physical Peramenters