Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 12 | 12 | 0 | ||
No of Bridges | 2 | 2 | 2 | 0 |
17W140 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 1440/।।।(2)/11-05(प्रा0आ0)/2010 दिनांक 28-03-2011
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 151.20 Lacs
Resanction Cost : 151.20 Lacs
Exp. Upto Last Fy : 7.24 Lacs
For CFY 2024-2025
Remaining : 143.96 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 7.24 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
13 years 1 month ago
28 Mar 2011
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 03: DM
Bottelneck: CA Land
क्षतिपूरक वृक्षारोपण हेतु भूमि आतिथि तक प्राप्त न हेाने के कारण लम्बित। राजस्व विभाग से लगातार पत्राचार जारी, भूमि प्राप्त होने के उपरान्त ही अग्रिम कार्यवाही सम्भव होगी। -- as on 19-Feb-2024
Physical Peramenters