Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
17W142 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 2376/।।।(2)/16-42 (एम0एल0ए0)/ 2015 दिनांक 31-08-2016
TS Amount (lakhs) : 150.27 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
150.27
Resanction Cost :
150.27
Tentative Cost :
150.27
Exp. Upto Last Fy : 132.39
For CFY 2024-2025
Remaining : 17.88
Demand : 17.88
Allotment : 0.00
Exp in CFY : 10.95
Total Up to Date Exp : 143.34
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 75 %
Sanction on :
7 years 10 months ago
31 Aug 2016
Tentative Completion date:
1 month 3 weeks ago
24 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य पूर्ण । दीवारां एवं स्कपरों का कार्य प्रगति पर। -- as on 16-Dec-2023
Physical Peramenters