Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
Closed Work 17W299 :
Administrative Approval Detail : शा0 से0 949/।।।(2)18-43(एम0एल0ए0) /2017 टी0सी0-।। दिनांक 31-03-2021
TS Amount (lakhs) : 59.5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
59.50
Resanction Cost :
59.50
Tentative Cost :
59.50
Exp. Upto Last Fy : 23.88
For CFY 2024-2025
Remaining : 35.62
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 23.88
Work completed
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 100 %
Sanction on :
3 years 3 months ago
31 Mar 2021
Tentative Completion date:
1 year 9 months ago
30 Sep 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 00: Not Started
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 13-Dec-2022
Physical Peramenters