Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 110 | 110 | 110 | 0 |
17W319 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2120/।।।(2)/22-49(प्रा0आ0)/2018
TS Amount (lakhs) : 3298.4 Lacs
Financial Detail
Sanction Cost : 3,298.40 Lacs
Resanction Cost : 3,298.40 Lacs
Exp. Upto Last Fy : 2,043.14 Lacs
For CFY 2024-2025
Remaining : 1,255.26 Lacs
Demand : 1,255.26 Lacs
Allotment : 114.33 Lacs
Exp in CFY : 1.19 Lacs
Total Up to Date Exp : 2,044.34 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 54 %
Up to Date : 69 %
Sanction on :
1 year 11 months ago
09 Jun 2022
Tentative Completion date:
2 days 14 hours ago
31 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सेतु के इरेक्शन व लाॅन्चिंग का कार्य अन्तिम चरण में है, जिसके अन्तर्गत समस्त स्टील कार्य 31 मई 2024 तक समाप्त होना लक्षित है। -- as on 22-May-2024