Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
17W341 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाइल संख्या 36352 लोक निर्माण विभाग अनुभाग 2
TS Amount (lakhs) : 223.34 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
223.34
Resanction Cost :
223.34
Tentative Cost :
223.34
Exp. Upto Last Fy : 25.39
For CFY 2024-2025
Remaining : 197.95
Demand : 192.00
Allotment : 100.00
Exp in CFY : 2.01
Total Up to Date Exp : 27.40
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
1 year 3 months ago
29 Mar 2023
Tentative Completion date:
2 months 2 weeks from now
04 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी1 बिछाने का कार्य एवं जी2 एकत्रीकरण का प्रगति पर -- as on 27-Jun-2024