Work Profile Report [17W41]

fपथौ0 मे कठपfतया गुडोली से दौला मोटर मार्ग का fनर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : 2884/(1)111-2/2006-41 दि0 10.11.06

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

62.30

Resanction Cost :

62.30

Tentative Cost :

62.30

Exp. Upto Last Fy :

3.30

For CFY 2025-2026

Remaining :

59.00

Demand :

59.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

3.30

Alignment Approved

Sanction on : 18 years 8 months ago

10 Nov 2006

Physical Progress:

At start of FY 2025-2026 :

5 %

Up to Date :

10 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3.5
3.5
3.5
-

Remark

view all

भारत सरकार के पत्रांक 8बी०/यू०सी०पी०/06/07/023/023/एफ०सी० दिनांक 28.02.2025 के द्वारा विधिवत स्वीकृति प्राप्त -- as on 07-Aug-2025

Rating : 5

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: