Work Profile Report [17W439]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E-File No. -64236/2023 Lok Nirman Anubhag-2 Date 27-03-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
94.86
Resanction Cost :
94.86
Tentative Cost :
94.86
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
94.76
Demand :
69.84
Allotment :
24.82
Exp in CFY :
24.82
Total Up to Date Exp :
24.92
Construction Started
Sanction on : 8 months 2 weeks ago
27 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
45 %
Tentative Completion date on : 2 months 4 weeks from now
14 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान एवं मलवा निस्तारण का कार्य प्रगति पर है| -- as on 01-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: