Work Profile Report [18W170]

जनपद चम्पावत के विधानसभा क्षेत्र लोहाघाट में के अन्तर्गत मूलाकोट काण्डे भुईया मोटर मार्ग का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 1466/।।।(2)/14-71(प्रा0आ0)/2013 दि 04 मार्च, 2014

TS Amount (lakhs) : 58.8 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

58.50

Resanction Cost :

58.50

Tentative Cost :

58.50

Exp. Upto Last Fy :

52.72

For CFY 2025-2026

Remaining :

5.78

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

52.72

Work completed

Sanction on : 11 years 10 months ago

04 Mar 2014

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 1 year 9 months ago

31 Mar 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
10
10
10
-

Remark

view all

प्रथम चरण का कार्य पूर्ण। द्वितीय चरण की स्वीकृति प्राप्त। वर्तमान में 80 प्रतिशत मुआवजे का भुगतान कर लिया गया है। कास्तकारों के उपस्थित न होने के कारण भुगतान में विलम्ब हो रहा है। -- as on 02-Jan-2026

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: