Work Profile Report [18W628]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : ई पत्रावली संख्या . 19329, लोक निर्माण अनुभाग-2 देहरादून: दिनाॅक 10-11-2022
TS Amount (lakhs) : 88.79 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
88.79
Resanction Cost :
88.79
Tentative Cost :
52.00
Saving
36.79
Exp. Upto Last Fy :
22.82
For CFY 2024-2025
Remaining :
65.97
Demand :
30.00
Allotment :
0.00
Exp in CFY :
24.40
Total Up to Date Exp :
47.22
Construction Started
Sanction on : 1 year 9 months ago
10 Nov 2022
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
75 %
Tentative Completion date on : 2 weeks 2 days ago
31 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 36.79 has been recorded as expected cost of work reduced from 88.79 to 52.00 . -- as on 22-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand