Work Profile Report [18W692]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई पत्रावली सं0 36717 दि0 28-3-2023
TS Amount (lakhs) : 66.15 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
66.15
Resanction Cost :
66.15
Tentative Cost :
66.15
Exp. Upto Last Fy :
58.41
For CFY 2025-2026
Remaining :
7.74
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
58.41
Work completed
Sanction on : 2 years 4 months ago
28 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 3 months ago
26 Apr 2024
Actual Completion Date : 1 year 2 months ago
02 Jun 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 28-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: