Administrative Approval Detail : जिलाधिकारी चम्पावत का पत्रांक 348/जि0यो0-प्र0वि0स्वी0/2023-24 दिनाॅक 30 जून, 2023
TS Amount (lakhs) : 15 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
15.00
Resanction Cost :
15.00
Tentative Cost :
15.00
Exp. Upto Last Fy :
7.50
For CFY 2024-2025
Remaining :
7.50
Demand :
7.50
Allotment :
7.50
Exp in CFY :
0.00
Total Up to Date Exp :
7.50
Construction Started
Sanction on : 1 year 5 months ago
30 Jun 2023
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
55 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर । -- as on 14-Aug-2024