Work Profile Report [18W720]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी चम्पावत का पत्रांक 348/जि0योज0-प्र0वि0स्वी0/2023-24 दिनांक 30 जून 2023
TS Amount (lakhs) : 24 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
24.00
Resanction Cost :
24.00
Tentative Cost :
24.00
Exp. Upto Last Fy :
5.00
For CFY 2025-2026
Remaining :
19.00
Demand :
5.90
Allotment :
5.90
Exp in CFY :
0.00
Total Up to Date Exp :
5.00
Work completed
Sanction on : 2 years 4 months ago
30 Jun 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मार्ग की लम्बाई 0.500 किमी0 है, जिसमें पार्ट -।। का कार्य पूर्ण। -- as on 31-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: