Administrative Approval Detail : ई पत्रावती सं0- 65756 पर्यटन अनुभाग, देहरादून, दिनांक 05 मार्च 2024
TS Amount (lakhs) : 427.24 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1253.28
Resanction Cost :
1253.28
Tentative Cost :
1253.28
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
1,253.28
Demand :
120.00
Allotment :
501.00
Exp in CFY :
133.87
Total Up to Date Exp :
133.87
Construction Started
Sanction on : 1 year 8 months ago
05 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
15 %
Tentative Completion date on : 10 months 1 day from now
24 Sep 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Raft footing work in progress -- as on 07-Oct-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: