Work Profile Report [18W918]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासन सं0 869-III-3-2025/सी0आर0आई0एफ0/ई0-7493 दिनांक 18.07.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4285.49
Resanction Cost :
4285.49
Tentative Cost :
4285.49
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
4,285.49
Demand :
823.00
Allotment :
1,718.00
Exp in CFY :
426.34
Total Up to Date Exp :
426.34
Construction Started
Sanction on : 4 months 4 weeks ago
18 Jul 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
15 %
Tentative Completion date on : 1 year 6 days from now
23 Dec 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दीवारों का कार्य प्रगति पर है।
प्लान्ट स्थापित कर लिया गया है।
-- as on 03-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2025 PWD Uttarakhand