Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 8 | 0 |
19W129 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 1440/।।।(2)/11-05(प्रा0आ0) दिनांक 28-03-2011
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 100.80 Lacs
Resanction Cost : 100.80 Lacs
Exp. Upto Last Fy : 4.36 Lacs
For CFY 2024-2025
Remaining : 96.44 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 4.36 Lacs
Survey work done
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
13 years 1 month ago
28 Mar 2011
Tentative Completion date:
7 months 2 weeks from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 07: Nodal
Bottelneck: Long Term Forest Approval
मार्ग की के0एम0एल0 पैलीगन फाईल आई0टी0 सेल देहरादून से प्राप्त कर अपलोड करने के पश्चात वर्तमान में प्रस्ताव नोडल अधिकारी स्तर पर। -- as on 26-Apr-2024
Physical Peramenters