Work Profile Report [19W129]

मुख्यमंत्री ग्रामीण सड़क संयोजन योजना के अन्तर्गत विकास खण्ड चम्पावत में बसौटी-रौकुॅंवर मोटर मार्ग का विस्तार।

    Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0 सं0 1440/।।।(2)/11-05(प्रा0आ0) दिनांक 28-03-2011

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

100.80

Resanction Cost :

100.80

Tentative Cost :

100.80

Exp. Upto Last Fy :

4.36

For CFY 2025-2026

Remaining :

96.44

Demand :

0.00

Allotment :

0.25

Exp in CFY :

0.00

Total Up to Date Exp :

4.36

Survey work done

Sanction on : 14 years 2 weeks ago

28 Mar 2011

Physical Progress:

At start of FY 2025-2026 :

20 %

Up to Date :

20 %

Tentative Completion date on : 3 months 1 week ago

31 Dec 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
8
8
8
-

Remark

view all

क्षतिपूरक वृक्षारोपण हेतु अवनत भूमि के स्थान पर सिविल सोयम भूमि उपलब्ध कराने हेतु आपत्ति को प्राप्त।, सिविल सोयम भूमि उपलब्ध कराने हेतु जिलाधिकारी महोदय को पत्र लिखा गया है। दिनांक 16.11.2024 को संयुक्त निरीक्षण किया गया। संयुक्त निरीक्षण उपरान्त सिविल भूमि उपलब्ध नही हो पायी है। भूमि उपलब्ध होने के उपरान्त अग्रिम आवश्यक कार्यवाही की जायेगी। -- as on 08-Apr-2025

Rating : 20

Forest Case Pending At : 03: DM

Hindrance / Bottleneck : Long Term Forest Approval