Work Profile Report [19W129]

मुख्यमंत्री ग्रामीण सड़क संयोजन योजना के अन्तर्गत विकास खण्ड चम्पावत में बसौटी-रौकुॅंवर मोटर मार्ग का विस्तार।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0 सं0 1440/।।।(2)/11-05(प्रा0आ0) दिनांक 28-03-2011

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

100.80

Resanction Cost :

100.80

Tentative Cost :

100.80

Exp. Upto Last Fy :

4.36

For CFY 2024-2025

Remaining :

96.44

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

4.36

Survey work done

Sanction on : 13 years 7 months ago

28 Mar 2011

Physical Progress:

At start of FY 2024-2025 :

20 %

Up to Date :

20 %

Tentative Completion date on : 1 month 1 week from now

31 Dec 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
8
8
0.000
8
0.000
0.000

Remark

view all

वर्तमान में प्रस्ताव भारत सरकार स्तर पर। सिविल सोयम भूमि उपलब्ध कराने हेतु आपत्ति, जिलाधिकारी महोदय को पत्र लिखा गया है। -- as on 28-Oct-2024

Rating : 20

Forest Case Pending At : 03: DM

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: