Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 21 | 21 | 21 | 0 |
19W260 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5353/।।। (2)/14-25 (प्रा0आ0)/2014
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
28.02
Resanction Cost :
28.02
Tentative Cost :
28.02
Exp. Upto Last Fy : 2.02
For CFY 2024-2025
Remaining : 26.00
Demand : 26.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.02
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
9 years 8 months ago
20 Oct 2014
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इस कार्य की द्वितीय चरण की स्वीकृति प्राप्त हो चुकी है। सिविल कार्य पूर्ण। नाप भूमि प्रभावित भाग हेतु मुआवजा प्रस्ताव गठित किये जा रहे है। -- as on 30-Apr-2021
Physical Peramenters