Work Profile Report [19W417]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : 1810/।।।(2)/17-55(एम0एल0ए0)/2017 दिनांक 23-08-2017
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
68.00
Resanction Cost :
68.00
Tentative Cost :
68.00
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
67.90
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Survey work done
Sanction on : 6 years 11 months ago
23 Aug 2017
Physical Progress:
At start of FY 2024-2025 :
5 %
Up to Date :
5 %
Tentative Completion date on : 4 months 2 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
समरेखन विवाद होने के कारण पुनः सर्वेक्षण उपरान्त सर्वेक्षण का कार्य पूर्ण। समरेखन प्रस्ताव गठित किया जा रहा है। -- as on 02-Feb-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: