Work Profile Report [19W671]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E-File No. 35871 Dated : 15-12-2022
TS Amount (lakhs) : 1690.28 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1783.33
Resanction Cost :
1783.33
Tentative Cost :
1783.33
Exp. Upto Last Fy :
933.85
For CFY 2024-2025
Remaining :
849.48
Demand :
849.48
Allotment :
772.45
Exp in CFY :
772.45
Total Up to Date Exp :
1,706.30
Work completed
Sanction on : 2 years 4 weeks ago
15 Dec 2022
Physical Progress:
At start of FY 2024-2025 :
70 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 week ago
31 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष।(08/2024) -- as on 06-Sep-2024