Work Profile Report [19W698]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E file no-35984
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
605.68
Resanction Cost :
605.68
Tentative Cost :
605.68
Exp. Upto Last Fy :
378.46
For CFY 2024-2025
Remaining :
227.22
Demand :
227.22
Allotment :
223.62
Exp in CFY :
223.62
Total Up to Date Exp :
602.07
Work completed
Sanction on : 1 year 4 months ago
31 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
76 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 4 days ago
30 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। (11/2024) -- as on 04-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand