Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 21.875 | 21.875 | 10.175 | 11.7 | 11.700 | 0.000 |
19W698 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E file no-35984
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
605.68
Resanction Cost :
605.68
Tentative Cost :
605.68
Exp. Upto Last Fy : 378.46
For CFY 2024-2025
Remaining : 227.22
Demand : 227.22
Allotment : 0.00
Exp in CFY : 112.42
Total Up to Date Exp : 490.87
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 80 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
6 months 17 hours from now
18 Jan 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डी0बी0एम0 एवं बी0सी0 तथा माइक्रोसरफेसिंग का कार्य पूर्ण। पैदल मार्ग में टाईल्स निर्माण का कार्य पूर्ण। वर्तमान में पूर्णागिरी मेले के कारण अन्य सिविल कार्य बाधित हंै। -- as on 01-Jul-2024
Physical Peramenters