Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9.885 | 9.885 | 4.150 | 5.735 | 5.735 | 0.000 |
19W742 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : UK. Gov. E File No. 31805/55 Dated : 28-12-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
326.19
Resanction Cost :
326.19
Tentative Cost :
326.19
Exp. Upto Last Fy : 49.50
For CFY 2024-2025
Remaining : 276.69
Demand : 276.69
Allotment : 0.00
Exp in CFY : 211.06
Total Up to Date Exp : 260.56
Construction Started
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 80 %
Sanction on :
6 months 2 weeks ago
28 Dec 2023
Tentative Completion date:
1 month 3 weeks from now
14 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
9.885 किमी के सापेक्ष 9.450 किमी मे SDBC का कार्य पूर्ण शेष कार्य प्रगति पर है -- as on 29-Jun-2024
Physical Peramenters