Work Profile Report [19W743]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : Uk. Gov. E-File No. 31805/55 Dated : 28-12-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
638.52
Resanction Cost :
638.52
Tentative Cost :
638.52
Exp. Upto Last Fy :
0.65
For CFY 2024-2025
Remaining :
637.87
Demand :
637.87
Allotment :
547.58
Exp in CFY :
547.58
Total Up to Date Exp :
548.23
Construction Started
Sanction on : 10 months 3 weeks ago
28 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
5 %
Up to Date :
85 %
Tentative Completion date on : 2 weeks 6 days from now
14 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
10.000 किमी.लंबाई में हाॅटमिक्स बी0सी0 का कार्य पूर्ण व 7.000 किमी0 लंबाई में सिविल कार्य पूर्ण , शेष कार्य प्रगति पर। -- as on 13-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand