Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10.34 | 10.34 | 0.000 | 10.34 | 10.340 | 0.000 |
19W743 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : Uk. Gov. E-File No. 31805/55 Dated : 28-12-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
638.52
Resanction Cost :
638.52
Tentative Cost :
638.52
Exp. Upto Last Fy : 0.65
For CFY 2024-2025
Remaining : 637.87
Demand : 637.87
Allotment : 0.00
Exp in CFY : 348.17
Total Up to Date Exp : 348.82
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 85 %
Sanction on :
6 months 2 weeks ago
28 Dec 2023
Tentative Completion date:
4 months 3 weeks from now
14 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
10.000 किमी.लंबाई में हाॅटमिक्स बी0सी0 का कार्य पूर्ण व 7.000 किमी0 लंबाई में सिविल कार्य पूर्ण , शेष कार्य प्रगति पर। -- as on 13-Jul-2024
Physical Peramenters