Work Profile Report [19W746]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 256/III(3)/2024-01(C.R.I.F.)2022 Dated : 29-02-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2457.00
Resanction Cost :
2393.71
Tentative Cost :
2393.71
Exp. Upto Last Fy :
165.13
For CFY 2024-2025
Remaining :
2,228.58
Demand :
842.35
Allotment :
397.71
Exp in CFY :
397.71
Total Up to Date Exp :
562.84
Construction Started
Sanction on : 9 months 3 weeks ago
29 Feb 2024
Physical Progress:
At start of FY 2024-2025 :
5 %
Up to Date :
20 %
Tentative Completion date on : 5 months 2 weeks from now
14 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सिविल कार्य (दिवार स्कपर आदि ) का कार्य प्रगति पर है, BM/BCका कार्य प्रारम्भ। -- as on 28-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand