Work Profile Report [19W900]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शासनादेश संख्या 7349/III(2)/2024-01(प्रा0आ0)/2023 दिनांक 06/11/2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
224.13
Resanction Cost :
224.13
Tentative Cost :
224.13
Exp. Upto Last Fy :
219.54
For CFY 2025-2026
Remaining :
4.59
Demand :
4.59
Allotment :
2.50
Exp in CFY :
2.50
Total Up to Date Exp :
222.04
Work completed
Sanction on : 8 months 1 week ago
06 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
90 %
Up to Date :
100 %
Tentative Completion date on : 2 weeks 4 days ago
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण।(06/2025) -- as on 04-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: