Work Profile Report [19W928]

जनपद चम्पावत में विज्ञान भवन केन्द्र का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : E File No. ST-ESTB/UCOS/5/2022-XXXIV-INFORMATION TECHNOLOGY DEPARTMENT/I/199036/2024 DATED : 14-03-2024

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

5552.62

Resanction Cost :

5552.62

Tentative Cost :

5552.62

Exp. Upto Last Fy :

454.29

For CFY 2025-2026

Remaining :

5,098.33

Demand :

1,350.00

Allotment :

586.44

Exp in CFY :

586.44

Total Up to Date Exp :

1,040.73

Construction Started

Sanction on : 1 year 7 months ago

24 Mar 2024

Physical Progress:

At start of FY 2025-2026 :

10 %

Up to Date :

40 %

Tentative Completion date on : 3 months 1 week from now

26 Feb 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Buildings
5
5
0
5
0
0

Remark

view all

1- रेजिडेन्स बिल्डिंग में आर0सी0सी0 फे्रम्ब्ड स्ट्रक्चर/ब्रिकवर्क का कार्य पूर्ण, प्लास्टर प्रगति पर।
2- कैफेटेरिया बिल्डिंग में भूतल की स्लैब में कंक्रीटिंग का कार्य पूर्ण।
3- साइंस गैलरी में प्रथम तल की ग्रिड 1 से 8 तक स्लैब कंक्रीटिंग का कार्य पूर्ण, ग्राउण्ड फ्लोर में ब्रिक वर्क का कार्य पूर्ण। प्रथम तल में ब्रिक वर्क का कार्य प्रगति पर।
4- आॅडिटोरियम ब्लाॅक में प्लीन्थ लेबल तक का कार्य पूर्ण। भूतल हेतु काॅलम में स्टील का कार्य प्रगति पर।
5- प्लेनेटोरियम ब्लाक में फुटिंग का कार्य प्रगति पर।
6- रोड बाउन्ड्री का कार्य प्रगति पर।
-- as on 12-Nov-2025

Rating : 124

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: