Work Profile Report [19W928]

जनपद चम्पावत में विज्ञान भवन केन्द्र का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : E File No. ST-ESTB/UCOS/5/2022-XXXIV-INFORMATION TECHNOLOGY DEPARTMENT/I/199036/2024 DATED : 14-03-2024

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

5552.62

Resanction Cost :

5552.62

Tentative Cost :

5552.62

Exp. Upto Last Fy :

454.29

For CFY 2025-2026

Remaining :

5,098.33

Demand :

1,350.00

Allotment :

582.51

Exp in CFY :

582.51

Total Up to Date Exp :

1,036.80

Construction Started

Sanction on : 1 year 6 months ago

24 Mar 2024

Physical Progress:

At start of FY 2025-2026 :

10 %

Up to Date :

35 %

Tentative Completion date on : 4 months 6 days from now

26 Feb 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Buildings
5
5
0
5
0
0

Remark

view all

1- रेजिडेन्सल बिल्डिंग में जी$3 स्ट्रक्चर का कार्य पूर्ण। द्वितीय तल तक ब्रिक वर्क का कार्य पूर्ण। शेष कार्य प्रगति पर।
2- कैफेटेरिया ब्लाॅक में भू-तल की स्लैब में स्टील बाइन्डिंग का कार्य प्रगति पर।
3- साइंस गैलरी में भू-तल की स्लैब का कार्य पूर्ण। प्रथम तल की स्लैब 50 प्रतिशत पूर्ण। शेष कार्य प्रगति पर।
4- आॅडिटोरियम ब्लाक में प्लीन्थ लेबल तक का कार्य 80 प्रतिशत पूर्ण।
5- प्लेनिटोरियम ब्लाक में फुटिंग का कार्य प्रंगति पर।
-- as on 14-Oct-2025

Rating : 124

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: