Work Profile Report [1W100]

अल्मोड़ा में मजखाली-दिगोटी मो0 मार्ग मजेटी ग्राम तक मो0 मार्ग निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0स0 2490/।।। -2/08-61(प्रा0आ0)/07 दिनांक 25.07.08

TS Amount (lakhs) : 140 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

140.00

Resanction Cost :

140.00

Tentative Cost :

140.00

Exp. Upto Last Fy :

91.80

For CFY 2024-2025

Remaining :

48.20

Demand :

25.00

Allotment :

24.59

Exp in CFY :

24.59

Total Up to Date Exp :

116.39

Work completed

Sanction on : 16 years 5 months ago

25 Jul 2008

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 1 year 8 months ago

31 Mar 2023

Actual Completion Date : 1 year 8 months ago

31 Mar 2023

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
4
4
4.000
0
0.000
0.000

Remark

view all

कार्य पूर्ण दायित्व शेष। -- as on 21-Dec-2024

Rating : 100

Forest Case Pending At : 20: Kattan

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: