Work Profile Report [1W235]

जनपद अल्मोड़ा में सुयालबाड़ी-गंगरकोट के मध्य झूला पुल का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : श्शासनादेश सं0-2062/।।।(2)/13-56(प्रा0आ0) /2012 दिनांक 20 मार्च, 2013

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

6.48

Resanction Cost :

6.48

Tentative Cost :

6.48

Exp. Upto Last Fy :

6.05

For CFY 2024-2025

Remaining :

0.43

Demand :

0.43

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

6.05

Work completed

Sanction on : 11 years 4 months ago

20 Mar 2013

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

0 %

Tentative Completion date on : 4 years 4 months ago

31 Mar 2020

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Bridge
1 (80m)
1 (80m)
1 (80m)
-

Remark

view all

प्रथम चरण का कार्य पूर्ण। कार्य के द्वितीय चरण की स्वीकृति प्राप्त जिसके अन्तर्गत कार्य पूर्ण। -- as on 30-Nov-2020

Rating : 100

Forest Case Pending At : 01: Withdraw

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: